Ice Arena Renovation
Progress is well underway on the Birmingham Ice Arena Renovation/Addition Project. The arena, utilized by more than 6,000 people each year, will benefit from the following upgrades: locker room expansion and remodel of the existing locker rooms, adding an additional locker room and dedicated team locker room, a new observation area and meeting room space, and new concession area upgrades.
Progress is well underway on the Birmingham Ice Arena Renovation/Addition Project. The arena, utilized by more than 6,000 people each year, will benefit from the following upgrades: locker room expansion and remodel of the existing locker rooms, adding an additional locker room and dedicated team locker room, a new observation area and meeting room space, and new concession area upgrades.
-
September 2021 Dashboard Report
Share September 2021 Dashboard Report on Facebook Share September 2021 Dashboard Report on Twitter Share September 2021 Dashboard Report on Linkedin Email September 2021 Dashboard Report linkView the September 2021 Dashboard Report(External link) from Plante Moran Cresa for a complete list of project highlights and the upcoming project schedule.
-
August 2021 Parks and Recreation Board Update
Share August 2021 Parks and Recreation Board Update on Facebook Share August 2021 Parks and Recreation Board Update on Twitter Share August 2021 Parks and Recreation Board Update on Linkedin Email August 2021 Parks and Recreation Board Update linkView Plante Moran Cresa's update to the Parks & Recreation Board on August 10, 2021 here.
-
August 2021 Dashboard Report
Share August 2021 Dashboard Report on Facebook Share August 2021 Dashboard Report on Twitter Share August 2021 Dashboard Report on Linkedin Email August 2021 Dashboard Report linkView the August 2021 Dashboard Report from Plante Moran Cresa for a complete list of project highlights and the upcoming project schedule.
-
July 2021 Dashboard Report
Share July 2021 Dashboard Report on Facebook Share July 2021 Dashboard Report on Twitter Share July 2021 Dashboard Report on Linkedin Email July 2021 Dashboard Report linkView the July 2021 Dashboard Report from Plante Moran Cresa for a complete list of project highlights and the upcoming project schedule.
-
June 2021 Dashboard Report
Share June 2021 Dashboard Report on Facebook Share June 2021 Dashboard Report on Twitter Share June 2021 Dashboard Report on Linkedin Email June 2021 Dashboard Report linkView the June 2021 Dashboard Report from Plante Moran Cresa for a complete list of project highlights and the upcoming project schedule.
-
June 2021 Parks & Recreation Board Update
Share June 2021 Parks & Recreation Board Update on Facebook Share June 2021 Parks & Recreation Board Update on Twitter Share June 2021 Parks & Recreation Board Update on Linkedin Email June 2021 Parks & Recreation Board Update linkView Plante Moran Cresa's update to the Parks & Recreation Board on June 1, 2021 here. Highlights from the previous month include the demolition of bleachers, main rink slab, mechanical equipment, ceilings, lights, and flooring.
-
May 2021 Dashboard Report
Share May 2021 Dashboard Report on Facebook Share May 2021 Dashboard Report on Twitter Share May 2021 Dashboard Report on Linkedin Email May 2021 Dashboard Report linkView the May 2021 Dashboard Report from Plante Moran Cresa for a complete list of project highlights and the upcoming project schedule.
-
Project Updates
Share Project Updates on Facebook Share Project Updates on Twitter Share Project Updates on Linkedin Email Project Updates linkJune 1, 2021 - Selective demolition is continuing this week. Masonry opening infill has begun. Rink perimeter slab is being poured. Underground plumbing is occurring.
May 18, 2021 - Selective demolition is still continuing this week. Slab removal in the Ice Rink and perimeter is still in progress.
May 11, 2021 - The construction fence around the Ice Arena was installed on May 6th and 7th. We are still in the demolition phase of the project. The concrete floor slab demo occurred recently. Other demolition includes HVAC, plumbing, electrical. mechanical through next week. Updates will continue as they become available.
April 15, 2021 - The Birmingham City Commission approved the contract with CE Gleeson Constructor, Inc. to serve as the General Contractor for this upcoming work. The immediate next steps include some of the following tasks:
- Removing the rink contents
- Performing other interior pre-construction work
The contractor is now onsite. Download the construction notice for information about parking and access to Kenning Park during the project.January 11, 2021 - The City of Birmingham awarded the Birmingham Ice Arena Architectural and Engineering Services project to Andrus Architecture in the amount not to exceed $288,900.00. Ice Arena improvements will include the following:
1) Locker Room Expansion and Remodel of Existing Locker Rooms
2) Adding a Fifth Locker Room and Team Locker Room
3) New Observation Area and Meeting Room Space
4) New Concession Area Upgrades
Photos
Who's Listening
-
Director of Public Services
Email lwood@bhamgov.org -
Parks & Recreation Manager
Email claird@bhamgov.org
Background Documents
- Plante Moran Cresa’s Facilities Assessment Update 1-25-20
- Capital Planning and Consultant Services for Ice Arena Memo 12-6-19
- Capital Planning and Consultant Services for Ice Arena Memo 11-4-20
- Parks and Recreation Improvement Funding Update Presentation 1-26-19
- Facilities Assessment Update 1-26-19
- 2018 Parks and Recreation Ice Arena Survey Results
- Capital Planning and Consultant Services for Ice Arena Memo 6-12-18
- Plante Moran Cresa’s (PMC) Facility and Operational Assessment 12-11-18
- 2B 20210123 Ice Arena Financial Forecast.pdf (2.62 MB) (pdf)
- 20210308 City of Birmingham Workshop 3-8-21 revised.pdf (3.24 MB) (pdf)